Washtenaw County Road Work Projects for the Week of Oct. 12

This schedule includes Washtenaw County road work projects for the upcoming week: Monday, Oct. 12, through Sunday, Oct. 18, 2026.

Local county projects include:

  • Lima Township:
    • Lane restrictions on Dexter-Chelsea Road between Island Lake Road and Dancer Road, through Oct. 31 (utility work permit)
    • Intermittent lane restrictions on local soft surface roads, Oct. 1–31 (dust control)
    • Intermittent lane restrictions on Lima Center Road between Scio Church Road and Jerusalem Road, Oct. 13–16 (forestry work)
    • Intermittent lane restrictions on Sager Road between Waltrous Road and Fletcher Road, Oct. 16–21 (forestry work)
    • Daytime road closure on Wylie Road between Island Lake Road and Dexter-Chelsea Road, Oct. 16–20 (limestone resurfacing)
    • Intermittent lane restrictions on Jerusalem Road between Waltrous Road and Fletcher Road, Oct. 20–26 (forestry work)
  • Lima/Scio Townships: Intermittent lane restrictions on Dexter-Chelsea Road between Island Lake Road and Parker Road, through late November (B2B trail permit work)
  • Lyndon Township: Lane restrictions on Werkner Road, south of Island Lake Road to Stofer Road, and at the Stofer Road/Island Lake Road intersection, Oct. 6–30 (installation of high-friction surface)
  • Sylvan Township: Lane restrictions on Old US-12 between Fahrner Road and Pierce Road, Oct. 6–30 (installation of high-friction surface)

All schedules are subject to change due to weather or other circumstances.